Approving an ask in a common unit prices it but doesn't deliver machines of the right shape, in the right place, on time, so the gap needs an owner and a ledger.

The idea

The seed paper's second claim: approval is not allocation argued. Allocation here means placing demand on physical machines. A common unit lets unlike asks be compared and approved, but it doesn't source them.

Demand then passes seven steps: declared, approved, allocated, delivered, live, adopted, productive. Each has its own owner, and each can leak. Hixson and Guliani's lead-time table runs a similar line to "Ready to serve" [6]. The seven steps add adoption and productive use after capacity is live.

Seven-step funnel from Declared to Productive, with a named leak and owner at each gap.
From the seed paper, Figure 15. The steps after approval are where ownership most easily goes unassigned.Open full size

A common unit prices; it doesn't clear. Approved units must still become a CPU-to-memory ratio, storage and access rate, and a placement within latency limits [1]. They must also become hardware that exists in time.

The unit's weights decide which asks look cheap. A cost-weighted unit under-prices asks heavy on whatever is scarce. If memory binds and only standard machines exist, extra memory drags along cores nobody uses: stranded capacity. Microsoft's Pond paper measures the mirror case: "up to 25% of DRAM becomes stranded" as cores are allocated [57].

Not every gap is a failure. Three cases:

  • Capped issue limits approval to sourceable supply.
  • Designed over-issue sells entitlements beyond supply under a stated firmness class, as Borg does for low priorities [17].
  • The undesigned gap is an approval treated as firm that supply can't meet.

Until supply answers with a dated commit or a named gap, label an approval uncommitted.

The gap isn't new. Auxon reports requirements it could not satisfy [1]. The 2026 SRE chapter says capacity must reach "the right consumer, in the right location, at the right time" [7]. The seed paper adds an owner and a ledger.

Where it shows up on the map

  • Quarterly, portfolio row: asks are approved in a common unit, with shapes asked for. See the quarterly stage.
  • Monthly, portfolio and region rows: the fulfillment ledger; machines arrive and turn up; netting runs. See the monthly stage.
  • Weekly, region and unit rows: shortages, bridges, brokered trades. See the weekly stage.

How to use it

Keep a fulfillment ledger (mechanism 5). Per ask, track approved (gross), net, committed, allocated, delivered, live and adopted, with the firmness class. Planning carries the gap; each step's performer owns its entry.

Net with care. Netting sits between approved and allocated on the ledger. Subtract on hand, on order and due back from reclaim; add back what retires that current load depends on. Every one of those is a forecast, so give each a date and an owner. A draw on a stocked pool leaves a replenishment owed. A reclaim that doesn't happen looks like a supply failure. Many undesigned gaps are born in this netting argued.

Re-shape before you cut. It's nearly free before the order and costly after. In the SRE chapter's Meet case, doubling CPU and memory per instance halved the instance count [7].

Bridge, then charge the premium to its cause. When approved demand can't be sourced in time, you bridge. The levers, fastest first, are re-pegging a slipped launch's supply, reclaiming idle capacity, shifting demand and reallocating between tenants. Slower ones are deferring a decommission and third-party capacity. These speeds are the seed paper's judgment, not sourced figures. A bridge works only if arranged before you need it. Charge each premium to its cause, such as a late ask or a forecast miss. Spread across everyone, it teaches that late asks are free.

Clear by brokering. Matching a holder with a team that needs the same shape, place and time is Jevons's "double coincidence" [89]. Markets automate it for fungible, short-horizon resources [16, 18]. Elsewhere it runs on knowing who holds what argued.

In the running example, the forum approved Product A at 4 NMU because the intake asked only about CPU. The data A stores needs memory, and the cheapest fit is 4.8 NMU (illustrative). The 0.8 NMU gap goes on the ledger with a named owner.

Machine diagrams: four standard machines lack memory; eight strand half their cores; two standard plus two high-memory fit at 4.8 NMU.
From the seed paper, Figure 30. The cheapest fit, and the gap. Illustrative.Open full size

What goes wrong

  • Approval treated as delivery; the team learns of the gap at launch.
  • A reclaim or decommission in the netting doesn't happen, and looks like a supply failure.
  • Delivered-but-not-live backlogs age quietly at turn-up.
  • Bridge premiums spread across everyone, so late asks look free.

Where this comes from

Seed paper, Sections 1, 6, 6.1, 6.4, 7 and 9.2 (mechanism 5). The lead-time line is Hixson and Guliani's [6]. Placement limits and unsatisfied requirements come from Auxon [1]. Pooled quota, the Meet case and the right-consumer framing come from the 2026 SRE chapter [7]. Also cited: [16–18, 57, 89]. See also the commit-point method and buffers and reserves.

Drawn from the seed paper: Section 1, Section 6, Section 6.1, Section 6.4, Section 7, Section 9.2.