What happens at this cadence
The seed paper calls this cycle continuous steering. You arbitrate, broker, run bridges and keep the fulfillment ledger current (Section 9.1 of the seed paper). It serves live and configured launches, the right-hand end of the commit-point timeline. Most of the work is small and frequent. Its value is that problems surface while something can still move.
- Envelope: normally nothing new is decided here. If a cut or a supply slip lands mid-cycle, the cut line moves in the re-cut order agreed beforehand.
- Region or site: shortages in one shape at one site, moves between regions, and turn-up queues. Delivered-but-not-live is where backlogs quietly age argued.
- Portfolio: escalations, brokered trades and overrides, each logged. The ledger stays current.
- Launch: pre-launch tests measure the coefficient before launch [7]. Slips are recorded and supply is re-pegged.
- Unit: tuning, and admission control at the top of a peak [33]. The two alerts belong to post-launch.
Commit points that land here
Job placement and admission commit here, at Live, in minutes to days. Turn-up and allocation committed monthly; here you run the queue against the staffed rate. A bridge also has a lead time. It works on your clock only if it was arranged before you needed it (Section 6.4). So the weekly cycle mostly spends options set up earlier. See the map and commit points.
What you do
Run the bridges. When approved demand can't be sourced in time, you bridge, fastest lever first. Charge each premium to its cause, such as a late ask or a forecast miss. The full lever list is in approval and allocation.
Broker. One team holds capacity it doesn't need; another needs that shape, there, now. Resource, amount, place and time must all match. That knowledge comes from a weekly habit of asking teams what's coming and what's idle argued. Log every trade, so what the broker knows outlives the broker (Section 10.4).
Apply shortage rules agreed beforehand. A delivery short in one shape at one site needs its own rule: who goes short first. The forum agrees it in advance; supply carries it out. Written during the shortage, it's a negotiation (Section 9.3). Don't split a shortage pro rata: rules that reward bigger orders teach teams to pad [A5]. A ranked list doesn't reward padding argued.
Watch turn-up. A slipped batch queues at turn-up with everything else that slipped, so a supply slip often shows up twice. Per-site turn-up throughput often binds argued.
Test before launch. A configured declaration can carry a coefficient measured in pre-launch tests [7], rather than guessed. The SRE chapter suggests reusing its ratios in "pre-launch performance testing and A/B testing" [7]. Where the test disagrees with the declared coefficient, raise it now. See the coefficient.
Handle escalations and overrides openly. An override is allowed, but it is logged with what moved down, and its bridges are charged to it (Section 10.2).
Say no with a path forward. Under real scarcity, refuse in writing. Cite the binding dimension and the cut line. Offer a re-shaped ask, a phased launch, placement elsewhere or a dated slot next cycle. A refusal with no path gets routed around (Section 9.1).
Learning planners usually work this cycle on single services and launches. Practicing planners take the escalations and broker across the portfolio argued. See people and operating mechanisms.
The example, at this cadence
Product A's launch on Service X, from launch to about +3 months. All numbers are illustrative.
- Envelope. —
- Region or site. Without the method, X runs a bridge from launch until the high-memory machines arrive at +3, about a quarter. Four standard machines from the pool run for their memory, with their CPU stranded. The pool is owed four, with a date and an owner.
- Portfolio. A release of X has raised CPU per call, so the extra installed cores also come from bridges. Until they land, X runs inside its own buffers: a dated ledger item owned by X.
- Launch. The launch slips six weeks. Without the method, nobody records it. With the method (Appendix A): the slip is recorded, and the launch reserve is re-pegged to another X tenant. A pre-launch test might have caught the higher coefficient argued.
- Unit. CPU per call has risen from 2.5 ms to 3.125 ms, so CPU runs out first. With the method (Appendix A): admission control on launch day handles the transient spike, owned by A with X.
What goes wrong
- A bridge is arranged after it is needed, so it arrives too late to help.
- Shortage rules are written during the shortage, and the loudest team wins.
- Trades live in one person's head and become an invisible second forum.
- A "no" comes without a path, and demand routes around the plan.
- A launch's coefficient is first measured on live traffic, after the machines were bought.
How to tell it's working
The commit-point map's test applies: bridge premiums shrink, and fewer orders are placed after their commit point (mechanism 13). For the forum, watch decisions reopened and overrides; that has no failing test yet. The seed paper adds a shortage budget as an analogy, not a result. At a 4 : 1 ratio, about one launch in five should need a bridge at that layer (Section 10.2). Far fewer for two years suggests padding; far more suggests optimistic records.
What it hands on
From monthly: a ledger with named gaps, owned bridges and a ranked list. To post-launch: live launches, their measured coefficients, the bridge premiums and their causes, recorded slips, and replenishments still owed.
| Artifact | Mechanism | Owner | Comes from | Goes to |
|---|---|---|---|---|
| Fulfillment ledger: bridges, replenishments owed | 5 | Planning carries the gap; each performer owns its entry | Monthly ledger | Post-launch review |
| Forum decision log: overrides, brokered trades, escalations | 10 | Named executive forum, run by planning | Monthly ranked list | Post-launch; next quarterly re-rank |
| Commitment register: re-pegged supply | 11 | Supply chain, with planning and finance | Monthly commits | Post-launch scoring of promises |
| Declaration register: slips recorded | 12 | Declaring team; planning keeps it | Monthly Configured entries | Post-launch scoring |
Placing each artifact at this cadence is the guide's reading argued.
Where this comes from
Seed paper, Sections 5.2, 5.4, 6.2, 6.4, 6.5, 6.7, 7, 9.1, 9.3, 10.2, 10.4 and 13, and Appendix A. Pre-launch tests and the measuring loop come from the 2026 SRE chapter [7]. Its Meet case ran a daily loop asking whether there were enough resources for the load expected a week out, and bridged by borrowing from other teams [7]. Admission control at the top of a predictable peak follows Alibaba's account [33].