Questions, answered

Infrastructure capacity planning questions, answered

Short answers to the questions planners ask most. Each one links to the page that teaches it, and to The Commons, where planners argue it out.

Capacity here means computing infrastructure: machines, accelerators, networks, data centres and power. New to the field? Start with what infrastructure capacity planning is.

The basics

Is this the same as capacity planning for teams and sprints?

No. Many tools use capacity planning to mean people’s time on a team. This practice covers the capacity of computing infrastructure: machines, accelerators, storage, networks, data centres and power.

Read more: What is infrastructure capacity planning? · Discuss this in The Commons

What does a capacity planner do?

The capacity planning chapter of Site Reliability Engineering, second edition (2026), defines it as forecasting future demand and provisioning supply to meet it. This guide argues there is a third part: keeping the agreement that pays for it. The planner sits between the people who fund capacity, build it and use it, usually owning no capacity and no budget.

Read more: The work and the path · Discuss this in The Commons

How do I get started in capacity planning?

Follow one path. Read the one page, then four concepts: the coefficient, demand and declarations, commit points, and approval and allocation. Then work one case with the worksheet. If you come from another field, pick the door for your background.

Read more: Start by role · The one page · Discuss this in The Commons

Demand

How do you forecast demand for a launch with no history?

A trend can extend organic growth, but not a step change with no history. The substitute is a declaration: a signed statement of expected demand, in units the planner already prices. Check it against how comparable declarations turned out. It firms up in stages: intent, dated, configured, live and organic.

Read more: Demand and declarations · Join the live thread

What about demand nobody sees coming?

The SRE book’s 2026 capacity chapter meets unplanned demand with buffers, autoscaling and demand shaping. When nobody declared the step, what remains are buffers, bridges and, at the limit, admission control. In the one public case the seed paper reads, most slow layers’ commit points had already passed.

Read more: Limits: where this breaks · Buffers and reserves · Discuss this in The Commons

Supply and lead times

How far ahead do you have to order capacity?

It depends on the layer. Land, buildings and utility power take years. Long-haul network takes months to years, and machines and parts take quarters. Turn-up takes weeks per job. Plan on a cautious lead time, near the slow end of what you have seen. The guide argues late arrivals are common and early ones rare.

Read more: Supply layers and lead times · Discuss this in The Commons

What is a commit point?

A commit point is the last date a supply layer’s order can still be placed: its need date minus its cautious lead time. What matters there is how much of the expected demand is still uncertain when that layer must be ordered.

Read more: Commit points · Glossary · Discuss this in The Commons

How much headroom should I keep?

One line called headroom usually hides several buffers, each with its own owner and sizing. Size each one as a priced decision: compare the cost of running short with the cost of holding spare. Pooling demand is the main saving, though correlated demand erodes it.

Read more: Buffers and reserves · Discuss this in The Commons

Why do capacity plans miss even when the forecast was right?

The seed paper’s answer: approval is not allocation. Approved capacity still has to become the right shape, in the right place, on time, and reach the team that needs it. Demand passes through declared, approved, allocated, delivered, live, adopted and productive, and each step can leak.

Read more: Approval and allocation · Discuss this in The Commons

Cost and chargeback

How should shared infrastructure be charged back?

A caller’s bill is roughly volume, times the coefficient, times the rate. Then ask which question a price answers. The average loaded rate answers who pays. Long-run incremental cost answers whether to build. The shadow price answers who gets scarce capacity now.

Read more: The coefficient · Three prices · Discuss this in The Commons

How is capacity planning different from FinOps?

They look at the same fleets from two sides. As this practice sees the split, FinOps leads on seeing and allocating cost, cutting waste and buying commitments well. Capacity planning works on demand, supply, lead times and when to commit. They meet on rates, chargeback and commitments.

Read more: CPP and FinOps: who does what · Discuss this in The Commons

What is a coefficient, and why call it an agreement?

A coefficient is the amount of a resource a service uses per unit of the driver of its load, such as CPU time per request. The planner reads it as a load forecast and the caller reads it as a price. The seed paper argues it is an agreement, so it needs an owner, versions and restating at breaks.

Read more: The coefficient · The seed paper, Section 5 · Discuss this in The Commons

AI and accelerator fleets

How do you plan capacity for GPUs and AI accelerators?

The structure holds, but the units move. For the largest operators, by their own public account, the binding constraint has moved toward power. Topology is a shape, so a fleet can hold enough chips and still be unable to place a training run. A busy chip is not always a productive one.

Read more: AI and accelerator fleets · Buildings at AI density · Join the live thread

Why is a single price per token misleading?

The token is a non-uniform driver. Prefill and decode cost differently, so one price per token misprices prefill-heavy, decode-heavy and long-context work. An AI release is also two shapes: a transient inference spike on a persistent step.

Read more: AI and accelerator fleets · Discuss this in The Commons

Running the practice

How do you notice when resource-per-request numbers drift?

Pick a business driver, instrument it with the infrastructure, and compute the ratio continuously. Alert when the ratio shifts or consumption departs from the forecast, and route it to planning. Treat a shift as a new version with an owner, not a quiet edit.

Read more: The measuring loop · Discuss this in The Commons

When is a formal capacity planning process not worth it?

For small workloads, the SRE book’s 2026 capacity chapter says simple overprovisioning is often the best strategy. One way to decide: compare each supply layer’s lead time with how long a launch takes to firm up. Where supply is faster, react; where it is slower, that layer needs a commit point.

Read more: Scale it to the risk · Discuss this in The Commons

Your question isn’t here?

Ask it in The Commons. Good questions become answers on this page, credited by name if you want.