The Capacity
Planning Practice

A plain answer

What is infrastructure capacity planning?

Infrastructure capacity planning decides how much computing, storage, network, power and building capacity to have, where and by when, so expected demand is met at an agreed cost and risk.

Here, capacity planning means infrastructure, not people’s time on a team. It covers computing, storage, network and accelerators, and the space, power and contracts underneath them. It works across lead times from minutes to years, and across altitudes from a whole fleet down to one service.

Is this the same as capacity planning for teams and sprints?

No. Many tools use capacity planning to mean people’s time on a team. This practice covers the capacity of computing infrastructure: machines, accelerators, storage, networks, data centres and power.

How is capacity planning different from capacity management?

Capacity management, as ITIL describes it, is the wider practice of making sure services have the capacity and performance they need, now and later. Capacity planning is its forward-looking core. It decides what to add, where and when, often months or years ahead.

What does a capacity planner do?

The capacity planning chapter of Site Reliability Engineering, second edition (2026), defines it as forecasting future demand and provisioning supply to meet it. This guide argues there is a third part: keeping the agreement that pays for it. The planner sits between the people who fund capacity, build it and use it, usually owning no capacity and no budget. See The work and the path.

Why does capacity have to be planned so far ahead?

Each layer of supply has its own lead time. Cloud capacity can arrive in minutes, machines in months, and buildings and power in years. A plan has to commit each layer before its lead time runs out, while demand is still uncertain. See supply layers and lead times and commit points.

How is demand forecast for capacity?

Organic growth can be forecast from a trend. Launches, migrations and new customers arrive as steps, so a trend misses them. The practice asks for a declaration instead: a signed statement of expected demand, which firms up in stages. See demand and declarations.

Why do capacity plans miss even when the forecast was right?

The seed paper’s answer: approval is not allocation. Approved capacity still has to become the right shape, in the right place, on time, and reach the team that needs it. Demand passes through declared, approved, allocated, delivered, live, adopted and productive, and each step can leak. See approval and allocation.

What is a coefficient, and why call it an agreement?

A coefficient is the amount of a resource a service uses per unit of the driver of its load, such as CPU time per request. The planner reads it as a load forecast and the caller reads it as a price. The seed paper argues it is an agreement, so it needs an owner, versions and restating at breaks. See the coefficient.

How do you plan capacity for GPUs and AI accelerators?

The structure holds, but the units move. For the largest operators, by their own public account, the binding constraint has moved toward power. Topology is a shape, so a fleet can hold enough chips and still be unable to place a training run. A busy chip is not always a productive one. See AI and accelerator fleets.

Is there an open body of knowledge for infrastructure capacity planning?

Yes. The Capacity Planning Practice (CPP) is an open, non-commercial body of knowledge and community for infrastructure capacity planners, built in public from public sources and licensed CC BY-SA 4.0. It has a guide, a glossary, case studies and a seed paper, and practitioners meet in The Commons.

Where to go next